Arctic Icebreaker Coordinating Committee (AICC)
Agenda for Meeting
Chinook Room
USCG Integrated Support Center
Pier 36 ñ 1519 Alaskan Way
Seattle, Wa
November 13 & 14, 2003 (Thursday & Friday)
SCHEDULE FOR MEETING
Day 1: 0830-1700
o 0950-1010 morning breako 1200-1300 luncho 1430-1450 afternoon breako evening - Dinner at RADM Garrett's home
Day 2: 0830-1230
o 0950-1010 morning breako 1230 Adjourn if possible
AGENDA ITEMS
1. General business & reports.
* Review and approve minutes of last meeting: http://www.mlml.calstate.edu/unols/aicc/aicmt302/aicmt302.html
* Chair report.
a. AICC Action items
* UNOLS reports (Mike Prince)
a. FIC Report (Mike Prince)b. DESSC Report (Hedy Edmonds)c. RVOC Report (Dan Schwartz)d. RVTEC Report (Dale Chayes)
* Agency Reports
a. NSF/OPP (Simon Stephenson)b. NOAA (Kathy Crane)c. ONR (TBD)d. Others
* ARVOC - Palmer Replacement Update
* ARC report (Garry Brass)
* Coast Guard Icebreaker Operations (Headquarters) report
* Coast Guard Pacific Area report(s)
2. 2003 Science Operations:
HEALY: Arctic East - West Summer 2003 (AEWS '03)
* Canadian Archipelago Throughflow Study (CATS)
* Northwind Ridge, Chukchi Plateau and the Canada Basin bottom mapping
* Western Arctic Shelf Basin Interactions (SBI) project
* Western Arctic Shelf Basin Interactions (SBI) project- Page at UW/APL
2003 Whaling Impacts: Rebecca Woodgate
Update on 2003 U/W data collection: Dale Chayes
Scheduling of Post Cruise Debriefs: Lisa Clough
3. Scheduling and planning for 2004 & Beyond.
* Overview of Antarctic Ice conditions (Larry Lawver)
* Scheduling Update
o HEALYo POLAR SEAo POLAR STAR
* 2004 & 2005 Plans and Availability
* 2005 Beringia Expedition
* ARCUS Overview: Wendy Warnick
* Expeditionary Planning
* Combining Arctic and Antarctic oversight more effectively
4. Other Icebreakers/Foreign Clearances
* GLACIER restoration update
* CCG/RV AMUNDSEN (ex FRANKLIN)
* Overview of Foreign Icebreakers: Peter Minnett
* Any clearance issues?
5. Science Modifications, Infrastructure and Equipment
HEALY
* Planning for the 2004 dry-docking
o Seawater systems (LCDR Neil Meister)o Towing Bitto Other items
* High latitude communications
* Multi-beam system status & survey of sensors
* GPS aided inertial navigation system
* Other requirements and plans
o additional current equipment statuso berthing issueso radiation policy
POLARS
* SLEB science workshop
* Status of SLEB evaluation and mid-life planning
* What next?
EQUIPMENT PURCHASES
* Replacement of lost equipment procedures
* SBI equipment requests (list from 2003)
* Update on equipment needs for 2004
* Longer range plans
6. Science operations and technical support
* Status of :
o 2004 Arctic icebreaker technical support requirements.o Science Data Network - 2003 report and 2004 plans (ATG report)o Web site/cruise planning manual assistanceo Science planning documentation (HEALY & POLAR Cruise Planning Guides)
* Continuous collection of underway data
o 2004 planso Long range solutions
* Previous issues (update as needed)
o Helicopter operations concurrent with other science operations
7. AICC business and other issues
* Alaska Region Research Vessel (Dirk Kristensen)
* AICC membership
o Departing memberso New memberso Future needso Next Chair?
* AICC Communications (web page, email lists, etc.)
* Future Meetings - dates, venue, agenda
o Spring 2004 meeting (March in DC?)
* Outreach Plans and Objectives
* Anything else???